Alness Grid Sub Station, Mid Balnacraig - Battery Storage Facility

A 50 MW battery storage site in Highland, Scotland. Consented, not yet built. The developer on record is Balnacraig Battery Storage Limited.

Size
50 MW
Stage
Consented, not yet built
Council
Highland
Region
Scotland
Developer
Balnacraig Battery Storage Limited
Application made
November 2022
Consented
December 2023

What this stage usually means

Consented and not yet built: the window in which the build is let, from the main contractor and the high-voltage connection to civil works, fencing and security.