Clay Tye Farm Phase 2 - Storage Facility
A 50 MW battery storage site in Havering, London. Running. The developer on record is Harmony Energy Storage.
- Size
- 50 MW
- Stage
- Running
- Council
- Havering
- Region
- London
- Developer
- Harmony Energy Storage
- Application made
- June 2018
- Consented
- February 2020
- Construction started
- July 2022
- Running since
- March 2024
What this stage usually means
Running: operation and maintenance, monitoring, grounds and security contracts.
Stanfell sends new battery storage sites the morning after their record moves, with a reading for your trade and, where one is found, how to reach the developer.
Other battery storage sites in Havering
- Clay Tye Farm - Energy Storage Facility
200 MW. In planning. Havering, London.
- Clay Tye Farm Phase 1 - Storage Facility
50 MW. Running. Havering, London.
- Layhams Road - Battery Storage Facility
250 MW. Consented, not yet built. Bromley, London.
- Manor Farm, Dartford Road - Energy Storage System
212 MW. In planning. Bexley, London.
- North Cray Road - Battery Energy Storage System
200 MW. Refused. Bexley, London.
- Atcost Road - Battery Storage Facility
100 MW. In planning. Barking and Dagenham, London.
- Fair Oak Lane battery storage
50 MW. Refused. Kingston upon Thames, London.
- Mill Hill National Grid Substation battery storage
50 MW. Consented, not yet built. Barnet, London.