Coventry National Grid Substation battery storage

A 50 MW battery storage site in Coventry, West Midlands. Running. The developer on record is Pivot Power.

Size
50 MW
Stage
Running
Council
Coventry
Region
West Midlands
Developer
Pivot Power
Application made
July 2020
Consented
January 2021
Construction started
July 2022
Running since
December 2023

What this stage usually means

Running: operation and maintenance, monitoring, grounds and security contracts.