Harrington Franklin, Richborough Energy Park - Battery Storage
A 50 MW battery storage site in Dover, South East. Under construction. The developer on record is EDP Renewables.
- Size
- 50 MW
- Stage
- Under construction
- Council
- Dover
- Region
- South East
- Developer
- EDP Renewables
- Application made
- June 2022
- Consented
- December 2022
- Construction started
- December 2024
What this stage usually means
Being built: subcontract work, plant hire, site services and security are bought on site now.
Stanfell sends new battery storage sites the morning after their record moves, with a reading for your trade and, where one is found, how to reach the developer.
Other battery storage sites in Dover
- Elvington Battery Energy Storage
50 MW. In planning. Dover, South East.
- Wharf Road, Discovery Park - Battery Energy Storage
10 MW. Consented, not yet built. Dover, South East.
- Old Rides Farm, Leysdown Road - Battery Energy Storage System
1,000 MW. In planning. Swale, South East.
- Southampton Battery Energy Storage
1,000 MW. In planning. Southampton, South East.
- Stable Green, Sand Hill Lane - Battery Energy Storage System
600 MW. Consented, not yet built. Wealden, South East.
- Culham Science Centre, Clifton Hampden - Battery Storage Facility
500 MW. Consented, not yet built. South Oxfordshire, South East.
- East Claydon Battery Energy Storage
500 MW. Consented, not yet built. Buckinghamshire, South East.
- East Claydon Substation, East Claydon Road - Energy Storage
500 MW. In planning. Buckinghamshire, South East.
Battery storage sites in the South East · The companies behind them