Lackenby battery storage

A 50 MW battery storage site in Redcar and Cleveland, North East. Consent lapsed. The developer on record is EDF Energy Renewables.

Size
50 MW
Stage
Consent lapsed
Council
Redcar and Cleveland
Region
North East
Developer
EDF Energy Renewables
Application made
July 2019
Consented
October 2019

What this stage usually means

The consent ran out before a build started. Lapsed sites are sometimes applied for again.