Lackenby battery storage
A 50 MW battery storage site in Redcar and Cleveland, North East. Consent lapsed. The developer on record is EDF Energy Renewables.
- Size
- 50 MW
- Stage
- Consent lapsed
- Council
- Redcar and Cleveland
- Region
- North East
- Developer
- EDF Energy Renewables
- Application made
- July 2019
- Consented
- October 2019
What this stage usually means
The consent ran out before a build started. Lapsed sites are sometimes applied for again.
Stanfell sends new battery storage sites the morning after their record moves, with a reading for your trade and, where one is found, how to reach the developer.
Other battery storage sites in Redcar and Cleveland
- Teesworks Battery Storage Project
1,000 MW. Application withdrawn. Redcar and Cleveland, North East.
- Tesside GigaPark - Battery Energy Storage System
1,000 MW. Consented, not yet built. Redcar and Cleveland, North East.
- Old Hall Farm, Lackenby - BESS
244 MW. In planning. Redcar and Cleveland, North East.
- Wilton International, Greystones Road - Phase 1 battery storage
150 MW. Consented, not yet built. Redcar and Cleveland, North East.
- Greystones Road, Grangetown - Battery Energy Storage System
60 MW. Consented, not yet built. Redcar and Cleveland, North East.
- A171, Guisborough Woods - Battery Energy Storage System
28 MW. Consented, not yet built. Redcar and Cleveland, North East.
- Hawthorn Pit Green Energy Park - Battery Energy Storage System
1,000 MW. In planning. County Durham, North East.
- Hallfield Farm, Easington - Battery Storage
300 MW. In planning. County Durham, North East.
Battery storage sites in the North East · The companies behind them