Native River battery storage

A 57 MW battery storage site in Cheshire West and Chester, North West. Running. The developer on record is Varco Energy.

Size
57 MW
Stage
Running
Council
Cheshire West and Chester
Region
North West
Developer
Varco Energy
Application made
December 2020
Consented
April 2021
Construction started
July 2023
Running since
April 2025

What this stage usually means

Running: operation and maintenance, monitoring, grounds and security contracts.