Salisbury Substation battery storage
A 50 MW battery storage site in Wiltshire, South West. Running. The developer on record is SSE Renewables.
- Size
- 50 MW
- Stage
- Running
- Council
- Wiltshire
- Region
- South West
- Developer
- SSE Renewables
- Application made
- August 2019
- Consented
- December 2021
- Construction started
- September 2022
- Running since
- April 2024
What this stage usually means
Running: operation and maintenance, monitoring, grounds and security contracts.
Stanfell sends new battery storage sites the morning after their record moves, with a reading for your trade and, where one is found, how to reach the developer.
Other battery storage sites in Wiltshire
- Brockleaze, Neston Park Estate - Battery Energy Storage
450 MW. In planning. Wiltshire, South West.
- Norrington Gate Farm, Broughton Gifford - Battery Energy Storage Facility
150 MW. Consented, not yet built. Wiltshire, South West.
- Fairholme, Minety - Battery Storage
50 MW. Consented, not yet built. Wiltshire, South West.
- Stonehill Energy Storage
50 MW. Consented, not yet built. Wiltshire, South West.
- Stonehill Energy Storage / Upper Minety
50 MW. Running. Wiltshire, South West.
- Stonehill Energy Storage / Upper Minety
50 MW. Running. Wiltshire, South West.
- Minety North battery storage
50 MW. Abandoned. Wiltshire, South West.
- Melksham Substation East Storage
50 MW. Running. Wiltshire, South West.
Battery storage sites in the South West · The companies behind them