Tynemouth Energy Storage System (TESS)
A 25 MW battery storage site in North Tyneside, North East. Running. The developer on record is Enel (formerly Element Power).
- Size
- 25 MW
- Stage
- Running
- Council
- North Tyneside
- Region
- North East
- Developer
- Enel (formerly Element Power)
- Application made
- September 2016
- Construction started
- December 2018
- Running since
- May 2018
What this stage usually means
Running: operation and maintenance, monitoring, grounds and security contracts.
Stanfell sends new battery storage sites the morning after their record moves, with a reading for your trade and, where one is found, how to reach the developer.
Other battery storage sites in North Tyneside
- Standby Embedded Stor Power Plant - Battery storage
20 MW. Under construction. North Tyneside, North East.
- Teesworks Battery Storage Project
1,000 MW. Application withdrawn. Redcar and Cleveland, North East.
- Tesside GigaPark - Battery Energy Storage System
1,000 MW. Consented, not yet built. Redcar and Cleveland, North East.
- Hawthorn Pit Green Energy Park - Battery Energy Storage System
1,000 MW. In planning. County Durham, North East.
- Hallfield Farm, Easington - Battery Storage
300 MW. In planning. County Durham, North East.
- Old Hall Farm, Lackenby - BESS
244 MW. In planning. Redcar and Cleveland, North East.
- Worset Lane - Battery Energy Storage System
200 MW. Consented, not yet built. Hartlepool, North East.
- Spennymoor Greener Grid Park
200 MW. Consented, not yet built. County Durham, North East.
Battery storage sites in the North East · The companies behind them