Aston House Solar Farm
A 20 MW solar farm in Derbyshire Dales, East Midlands. Running. The developer on record is Solar century & Magnetar Solar.
- Size
- 20 MW
- Stage
- Running
- Council
- Derbyshire Dales
- Region
- East Midlands
- Developer
- Solar century & Magnetar Solar
- Application made
- July 2014
- Consented
- November 2014
- Construction started
- December 2014
- Running since
- March 2015
What this stage usually means
Running: operation and maintenance, monitoring, grounds and security contracts.
Stanfell sends new solar farms the morning after their record moves, with a reading for your trade and, where one is found, how to reach the developer.
Other solar farms in Derbyshire Dales
- Brailsford Solar Park, Main Road - Solar Panels
55 MW. In planning. Derbyshire Dales, East Midlands.
- Beacon Fen Energy Park
400 MW solar and 600 MW battery storage. Consented, not yet built. East Midlands.
- Green Hill Solar Farm & Battery Storage
500 MW solar and 500 MW battery storage. Consented, not yet built. East Midlands.
- Springwell, Lincoln - Springwell Solar Farm & Battery Storage
800 MW solar and 0 MW battery storage. Consented, not yet built. East Midlands.
- Great North Road Solar Park
800 MW solar and 0 MW battery storage. In planning. East Midlands.
- Meridian Solar Farm - Solar Farm
750 MW. In planning. East Midlands.
- One Earth Solar Farm
740 MW solar and 0 MW battery storage. Consented, not yet built. East Midlands.
- Cottam Solar Project
600 MW solar and 0 MW battery storage. Consented, not yet built. East Midlands.
Solar farms in the East Midlands · The companies behind them