Cleve Hill Solar Project

A 373 MW solar and 150 MW battery storage solar farm in South East. Running. The developer on record is Quinbrook Infrastructure Partners.

Size
373 MW solar and 150 MW battery storage
Stage
Running
Decided
Nationally, not by a council
Region
South East
Developer
Quinbrook Infrastructure Partners
Application made
November 2018
Consented
January 2021
Construction started
April 2023
Running since
July 2025

What this stage usually means

Running: operation and maintenance, monitoring, grounds and security contracts.