Wittering Ford Road, Barnack - Solar Photovoltaic Farm
A 11 MW solar farm in Peterborough, East of England. Consented, not yet built. The developer on record is Larkfleet limited.
- Size
- 11 MW
- Stage
- Consented, not yet built
- Council
- Peterborough
- Region
- East of England
- Developer
- Larkfleet limited
- Application made
- July 2023
- Consented
- November 2023
What this stage usually means
Consented and not yet built: the window in which the build is let, from the main contractor and the high-voltage connection to civil works, fencing and security.
Stanfell sends new solar farms the morning after their record moves, with a reading for your trade and, where one is found, how to reach the developer.
Other solar farms in Peterborough
- Malice Farm, French Drove - Solar Farm
50 MW. Consented, not yet built. Peterborough, East of England.
- Nutsgrove Farm, Thorney - Solar Array
50 MW. Consented, not yet built. Peterborough, East of England.
- Farms of Newborough solar farm
49 MW. Application withdrawn. Peterborough, East of England.
- Morris Fen (PV)
27 MW. Application withdrawn. Peterborough, East of England.
- Dogsthorpe, Welland Road - Solar Farm & Battery Storage
14 MW solar and 0 MW battery storage. Consented, not yet built. Peterborough, East of England.
- The Park Farm, Birds Corner - Battery Energy Storage
50 MW solar and 800 MW battery storage. In planning. Breckland, East of England.
- Sunnica Energy Farm (East and West)
500 MW solar and 8.8 MW battery storage. Consented, not yet built. East of England.
- East Park Energy
400 MW solar and 100 MW battery storage. In planning. East of England.
Solar farms in the East of England · The companies behind them