Titchfield Lane battery storage
A 49 MW battery storage site in Winchester, South East. Under construction. The developer on record is Balanced Grid Solutions.
- Size
- 49 MW
- Stage
- Under construction
- Council
- Winchester
- Region
- South East
- Developer
- Balanced Grid Solutions
- Application made
- December 2019
- Consented
- August 2020
- Construction started
- August 2023
What this stage usually means
Being built: subcontract work, plant hire, site services and security are bought on site now.
Stanfell sends new battery storage sites the morning after their record moves, with a reading for your trade and, where one is found, how to reach the developer.
Other battery storage sites in Winchester
- Widley Farm, New Down Lane - Battery Storage Facility
100 MW. In planning. Winchester, South East.
- Silkstead Farm, Poles Lane - Battery Energy Storage System
50 MW. Consented, not yet built. Winchester, South East.
- Lovedean Substation battery storage
50 MW. Application withdrawn. Winchester, South East.
- Winchester Battery Storage
19 MW. Running. Winchester, South East.
- Ash Farm, Titchfield Lane - Battery Storage
15 MW. Consented, not yet built. Winchester, South East.
- Stockbridge Road battery storage
10 MW. Consented, not yet built. Winchester, South East.
- Old Rides Farm, Leysdown Road - Battery Energy Storage System
1,000 MW. In planning. Swale, South East.
- Southampton Battery Energy Storage
1,000 MW. In planning. Southampton, South East.
Battery storage sites in the South East · The companies behind them